Expanding while the plant keeps running is one of the most common scenarios in industrial projects. For this potato processor, a growing receiving capacity meant three simultaneous expansions: an additional Wyma washing line, a new sorting zone for washed and unwashed potatoes, and a separate processing line for waste bins—with the weekend as the only window for breakdown support.
The complexity wasn’t limited to the technical aspects. Wyma and Loyu 2000, each with their own working methods and standards, had to integrate seamlessly with the Deprez installation. The project required tight coordination, quick decision-making, and proactive project management.
Back in 2022, during the initial design phase, the existing installation was designed with future expansion in mind. That forward-looking decision made integrating the new line significantly more practical. The design phase took about one month. During that time, all Deprez machines were precisely aligned with the Wyma and Loyu 2000 installations, with particular attention to interference points and interfaces.
Assembly was scheduled during weekend shutdowns so the plant could resume operations every Monday. This required close coordination between the customer, the controls partner, and the assembly team, with safety as a constant priority. On-site assembly was completed in just under two weeks. Each machine was not only installed but also fully wired and programmed, so the installation was immediately operational after each weekend window.