Adams Polendam logo

Ship Unloading System over Railway

At Adams Polendam along the Albert Canal, Deprez transitioned the transport of sand, gravel, and aggregate from road to water with an industry first: a tubular conveyor bridge over the railway connecting crane to storage.

Vraag, plan & oplossing

At Adams Polendam along the Albert Canal, Deprez transitioned the transport of sand, gravel, and aggregate from road to water with an industry first: a tubular conveyor bridge over the railway connecting crane to storage.

01 vraag

Adams Polendam aimed to unload sand and gravel at the quay and transfer it directly into the designated storage bunkers without additional truck traffic. The primary challenge: a railway runs parallel to the quay, and bicycle traffic along the public quay path had to remain completely unobstructed throughout installation.

02 plan

Deprez implemented an integrated transshipment and storage system. The belt conveyor was enclosed in a tubular bridge structure crossing over the railway. Using a fully automated control system and continuous monitoring via a continuous belt scale, the aggregates are delivered into the correct storage bunker.

03 oplossing

The result is a transshipment system with a throughput capacity of 600 tons per hour. Three 140-meter belt conveyors transfer all sand and gravel into 10 storage bays of 2,000 to 2,500 m³ each. Each barge shipment now replaces up to 100 truck runs for internal haulage from the quay to the facility, while completely eliminating the need for an additional wheel loader.

Resultaat

01

Single-operator control

02

Reduced energy costs, lower CO2 emissions

03

Elimination of safety risks and logistical bottlenecks

04
05
06
"Since the Deprez installation, our operations have run completely smoothly and predictably. What used to be a complex sequence of isolated handling steps is now handled by a single integrated system easily operated from a central station. A significant operational advance thanks to Deprez!"
Ronny Adams
Managing Director, Adams Polendam

Het volledige verhaal

The site conditions presented specific operational challenges. Located along a public canal-side bicycle path, the facility required uninterrupted bicycle traffic at all times. Specific security measures were also required to prevent climbing access to the structure.


Because the facility had to remain fully operational throughout construction, assembly was scheduled within a minimal footprint and executed by a compact two-man mechanical team to limit operational impact. The core of the engineering solution lay in conveying the aggregates through an enclosed tubular bridge across the railway, replacing secondary on-site truck haulage. As Deprez’s first installation crossing an active railway track, the project required strict attention to the structural design and static weight of the tube structure itself.

The system along the Albert Canal consists of a transshipment crane rated for up to 600 tons per hour, linked to three 140-meter belt conveyors equipped with tripper cars. Material is distributed across 10 storage bays with 5-meter-high retaining walls, each holding 2,000 to 2,500 m³ of sand or gravel. An enclosed tubular bridge measuring 24 meters long and 3 meters in diameter houses a belt conveyor that transfers all aggregate safely over the quay, bicycle path, and railway tracks in a fully secure structure. A mobile shuttle car travels along the conveyor to fill the bays in a controlled manner.

The installation includes an integrated traffic light system that interfaces with the crane via remote control, ensuring unloading occurs only when the handling line is fully operational and cleared.

To maintain ongoing plant operations during installation, on-site assembly time was engineered to an absolute minimum. As Deprez’s first railway-crossing project, it required meticulous structural preparation and precise logistical planning. This approach enabled the complete structural assembly to be executed safely and successfully in just four hours, with minimal operational disruption.

Meer cases

Frankrijk
bin & bulk · Bin handling · Receiving

From traditional to fully automatic receiving in bins

At Ferme des Arches, Deprez built a receiving and filling line for onions that already runs smoothly today, and is ready for tomorrow’s automatic control system.
België
only bulk · Bulk conveying · Crushing & screening

Future-proof relocation of existing machinery

Due to the planned expansion of the R4, the site in Wondelgem was forced to relocate. This necessity was turned into an opportunity, as AC Materials Ghent brings together the two former recycling centers in Wondelgem and Desteldonk at a new 15-hectare site at Kluizendonk.
Verenigd Koninkrijk
bin & bulk · Bin handling · Conveying systems

Phased logistics optimization for fresh produce market

With an emphasis on quality and processing that meets the highest food safety standards, Puffin supplies products from local growers to UK supermarkets. To efficiently accommodate growing capacity, Puffin partnered with Deprez for a phased optimization of the site.
België
only bulk · Bulk conveying · Bulk Storage

Streamlined route from soil remediation to storage bunkers

Bioterra Genk specializes in processing contaminated soil and mineral waste. The Deprez team developed a fully integrated internal conveyor system for the site, designed to ensure a streamlined flow from soil remediation to the storage bunkers.

Deel deze case