AC Materials aimed to build a state-of-the-art crushing and screening plant to operate more sustainably, efficiently, and economically. At the same time, the existing machines and belt conveyors, in service for about 20 years, were far from worn out. The question was therefore not only what a new site should look like, but also how valuable existing infrastructure could be integrated. Building a completely new installation was not a given from a budgetary perspective, especially during a period of rising raw material prices. Additionally, the physical relocation itself brought complexity: machines and belt conveyors up to 40 meters long and 5 meters high had to be moved from the old to the new site without compromising safety standards or future expansion possibilities.
Three principles were paramount in developing the plan: maximum reuse of existing machinery, a high-quality installation according to Deprez quality standards, and efficient logistics at the new site. Based on these, it was determined which main components could be fully reused after the necessary overhaul.
Water transport was chosen for the move between the old and new sites, a logical choice given the location of both sites. To make this possible, the existing installation was carefully planned for disassembly into larger sections, which significantly simplified subsequent reassembly and limited downtime. Certain parts were taken to Deprez workshops for modification, while other parts were completely redesigned and manufactured.
At the new site, the installation was equipped with extra-long belt conveyors, allowing a larger quantity of aggregates to be stocked immediately without wheel loaders, while accounting for future expansions. All machines and belt conveyors are equipped with the necessary stairs and platforms to ensure visual inspections and maintenance work can be performed safely.
Deprez upgraded existing infrastructure into a state-of-the-art crushing and screening plant. Through a smart layout, maximizing reuse, and making the right choices, Deprez was able to reduce the investment cost to approximately one-third of a completely new installation without sacrificing capacity. The site in Ghent will reliably process 250 to 300 tons of construction material per hour for the next 20 years, totaling 250,000 tons per year.