Future-proof relocation of existing machinery

Due to the planned expansion of the R4, the site in Wondelgem was forced to relocate. This necessity was turned into an opportunity, as AC Materials Ghent brings together the two former recycling centers in Wondelgem and Desteldonk at a new 15-hectare site at Kluizendonk.

Vraag, plan & oplossing

Due to the planned expansion of the R4, the site in Wondelgem was forced to relocate. This necessity was turned into an opportunity, as AC Materials Ghent brings together the two former recycling centers in Wondelgem and Desteldonk at a new 15-hectare site at Kluizendonk.

01 vraag

AC Materials wanted to consolidate the activities of two former recycling centers at a new site in the Port of Ghent, seeking a way to realize a crushing and screening plant while retaining existing machinery.

02 plan

Deprez developed a plan for full disassembly plus maximum reuse of existing components after overhaul, transport by water between the old and new sites, and an efficient, future-proof layout of machines and belt conveyors at the new location.

03 oplossing

The result is a revitalized and expanded installation that will reliably process 250 to 300 tons of construction material per hour for the next 20 years, with an investment cost of approximately one-third of a completely new installation and concrete energy savings thanks to updated logistics.

Resultaat

01

State of the art for 1/3 of the new price

02

Highly energy-efficient and CO2-reducing

03

Smart logistics for a sustainable recycling site

04
05
06

Het volledige verhaal

AC Materials aimed to build a state-of-the-art crushing and screening plant to operate more sustainably, efficiently, and economically. At the same time, the existing machines and belt conveyors, in service for about 20 years, were far from worn out. The question was therefore not only what a new site should look like, but also how valuable existing infrastructure could be integrated. Building a completely new installation was not a given from a budgetary perspective, especially during a period of rising raw material prices. Additionally, the physical relocation itself brought complexity: machines and belt conveyors up to 40 meters long and 5 meters high had to be moved from the old to the new site without compromising safety standards or future expansion possibilities.

Three principles were paramount in developing the plan: maximum reuse of existing machinery, a high-quality installation according to Deprez quality standards, and efficient logistics at the new site. Based on these, it was determined which main components could be fully reused after the necessary overhaul.

Water transport was chosen for the move between the old and new sites, a logical choice given the location of both sites. To make this possible, the existing installation was carefully planned for disassembly into larger sections, which significantly simplified subsequent reassembly and limited downtime. Certain parts were taken to Deprez workshops for modification, while other parts were completely redesigned and manufactured.

At the new site, the installation was equipped with extra-long belt conveyors, allowing a larger quantity of aggregates to be stocked immediately without wheel loaders, while accounting for future expansions. All machines and belt conveyors are equipped with the necessary stairs and platforms to ensure visual inspections and maintenance work can be performed safely.

Deprez upgraded existing infrastructure into a state-of-the-art crushing and screening plant. Through a smart layout, maximizing reuse, and making the right choices, Deprez was able to reduce the investment cost to approximately one-third of a completely new installation without sacrificing capacity. The site in Ghent will reliably process 250 to 300 tons of construction material per hour for the next 20 years, totaling 250,000 tons per year.

Meer cases

België
only bulk · Bulk conveying · Transshipment

Ship Unloading System over Railway

At Adams Polendam along the Albert Canal, Deprez transitioned the transport of sand, gravel, and aggregate from road to water with an industry first: a tubular conveyor bridge over the railway connecting crane to storage.
Frankrijk
bin & bulk · Bin handling · Receiving

From traditional to fully automatic receiving in bins

At Ferme des Arches, Deprez built a receiving and filling line for onions that already runs smoothly today, and is ready for tomorrow’s automatic control system.
Verenigd Koninkrijk
bin & bulk · Bin handling · Conveying systems

Phased logistics optimization for fresh produce market

With an emphasis on quality and processing that meets the highest food safety standards, Puffin supplies products from local growers to UK supermarkets. To efficiently accommodate growing capacity, Puffin partnered with Deprez for a phased optimization of the site.
België
only bulk · Bulk conveying · Bulk Storage

Streamlined route from soil remediation to storage bunkers